It looks like the City of Fall River is finally moving forward with demolishing the old Central Police Station — almost 30 years after it was last occupied — only for the Preservation Society of Fall River to ask, “What’s the rush?”
The City’s Building Commissioner, Glenn Hathaway, states that the building is a public health hazard and that the 12‑month mandatory demolition delay for historical buildings must be waived.
The Preservation Society argues that the Building Department has not provided any proof that the building poses an immediate public emergency, and that the Historical Commission should follow standard procedure and waive the demolition‑delay bylaw only if sufficient evidence is presented to the community.
While part of this (fair or not) feels like arguing that grandma deserves a second opinion just before the hospital pulls the plug, the reality is that this might be the best example of Fall River being completely inept at dealing with “historical” properties.
The Central Police Station was built in 1915 and served as Fall River’s primary police headquarters for 82 years. I’m sure those 82 years produced plenty of history and stories, but in some ways, it’s the 29 years since the station closed that are the most interesting.
The building has been put up for sale and sold repeatedly. Despite the constant turnover, none of the ownership changes ever resulted in meaningful improvements, and the building ultimately wound up back in the hands of the city.
Through all of this, the building’s condition has only worsened, and the citizens of Fall River — regardless of their opinions — have largely sat by passively, waiting for something to happen.
It seems that in the 29 years since the station became vacant, there were two major missed opportunities to do something with the property.
The first was in 2000, when the Old Police Station was seriously considered as part of a new courthouse complex. At the time, the state needed to either renovate the existing courthouse or build a new one. One proposal would have preserved both the original courthouse and the police station, connecting them with a new four‑story building.
I personally favored this plan. It would have kept the courthouse in its established location, and I believed the South Main Street site — where the Justice Center now stands — could have been used more effectively to revitalize downtown. Seniors living near the South Main Street site opposed the move, as did those who didn’t want the bus terminal relocated. There were some hollow statements about incorporating the bus terminal into the courthouse site, but that obviously never happened.
The second opportunity came in 2006, when the City Council initially voted to accept a bid from Anthony Cordeiro — only for the deal to fall apart amid questions about whether the city had conducted the sale properly. Preservationists likely wouldn’t have been thrilled anyway, as Cordeiro had discussed demolishing the building and constructing a new one, representing roughly a $4 million investment.
Cordeiro wanted to pay $25,000 for the property. Twenty years later, we’re talking about 56 times that amount just to tear the building down.
But let’s get back to the present — to finally tearing the building down, or allowing the Historical Commission to propose some way to save it in some form.
The reality is that it has been nearly 30 years of not only failing to decide what to do with this building, but also failing to market it effectively for any kind of redevelopment. And honestly, if you tore it down tomorrow and put up a parking lot, the lot would probably generate more revenue than the building ever has in its current state.
But that doesn’t mean we should just tear it down. I agree with the Preservation Society that the demolition delay exists for a reason, and the process should be followed. If the building is in such terrible condition that it poses an immediate threat to the community, then the Building Department should be able to provide reports and studies that make that clear.
This isn’t about delaying the inevitable for the sake of delay. It’s about having a mechanism that ensures we act with at least some degree of historical responsibility. The Central Police Station has been an eyesore for decades — 12 more months is not going to make a meaningful difference.
Could the Historical Commission have done something long before now? That’s a fair question, and one I’d love to ask its members. But the Commission hasn’t had the same membership for its entire 50‑year existence, and without digging into how long each member has served, it seems unfair to point fingers and say they should have acted sooner. Also, the Commission doesn’t actually have much power.
But one of the few powers they do have is this 12‑month demolition delay, and anyone frustrated that they’re not waiving it to speed up the wrecking ball should instead direct their frustration toward the many administrations that failed to develop any vision for this building — and perhaps toward themselves and their fellow citizens for not holding those elected officials more accountable.